Skip to main content

July Already?!


In the month since I last sat down to chronicle all the activity on the mountain, we have accomplished A LOT. The team from Ruotsalas has completed pouring concrete and backfilled the foundations for Towers 2-10. This leaves Tower 1 and all four terminal foundations to complete but is still a big milestone as it allows us to revegetate the access roads created to reach tower locations on the side of the hill.  The rest of the pours are much more easily accessible via pre-existing and solid roadways, meaning rainy weather is much less of a threat to our forward progress. 

Tower 9 foundation is backfilled with grass already growing. -7/8/2023

With the Tower foundations substantially completed, the focus shifts to the top and bottom terminal locations. At the bottom, we are undertaking a massive regrading project to improve skier access to the lift from both the east and the west sides. The loading mound of the former triple lift has been completely removed and redistributed at the bottom of Borealis (FKA Leelinaw). This will create a consistent downhill pitch from the foot of the hill all the way to the lift loading area. I'm excited for my first run down Borealis this season without having to push or skate my way uphill to the lift. To the east of the new terminal, up to 10 feet of material has been removed to create a consistent grade from Creekside all the way down to the loading area. 

Bottom terminal location before grading work began. - 06/20/2023

Grading work in progress showing the full removal of the Triple's loading ramp. - 6/21/2023

Finally Breaking Ground

Three months after we were meant to break ground on the drive terminal we are finally in the ground. We ran into a number of surprises earlier this spring when we first had utilities located. Within the 20' x 20' area that the top terminal foundation was meant to go we found the primary electrical service, water main, and greywater discharge lines for the Summit Chalet. All of these utilities needed to be relocated before we could begin excavation. Unfortunately getting the necessary permits in hand to complete this work took longer than expected. I appreciate the work of our partners at Xcel Energy, the Gogebic Range Water Authority, Section 32 Sewer Authority, C2AE, and Ruotsala's Construction in helping us to get this done as quickly as possible.

Despite the delays on this portion of the project, we are still on schedule for an on-time completion as we shifted the tower foundations to the start of the project when those weren't originally scheduled to be started until the 1st of July. Shovels hit the dirt at the top terminal site this past week and thanks to the quick work of the teams, we expect to pour the first round of concrete the second week of July.

Drive terminal forms await the first of two pours. - 7/7/2023

4th of July Parades

In our neighboring towns of Wakefield and Bessemer, the 4th of July is a big deal. The biggest event of the year for both communities. Naturally, we wanted to be a part of the celebration, so the team built a float and participated in both communities' parades on the fourth. The float was called, "Winter in July" and aimed to bring back memories of the cooler times from winter's past and raise excitement for many seasons to come at Snowriver. I really appreciate the dedication of those team members who volunteered to build the float and participate in the parade. Their efforts won us the best-decorated float in the Bessemer Parade! 


The Snowriver Parade Crew awaiting the start of the Wakefield Parade. - 7/4/2023

New Windows Are Here

Over 100 new windows and doors were delivered the first week of July. The team made quick work of getting them installed in the Lodge as nearly all of the old windows had already been removed in preparation. We've all been surprised by how clear a clean, new window truly is after years of looking through weathered glass. The entire Lodge at Jackson Creek will receive new windows for the guest rooms, lobby, restaurants, and the long hallway to the pool. Once fully trimmed out, these new windows are really going to dress the place up and of course, do a much better job keeping the rooms warm next winter. 

New windows freshly installed in The Lodge at Jackson Creek - 07/6/2023

In addition to The Lodge, a few of the Gabbro Suites and the entire Summit Chalet are also receiving brand-new windows. Thanks to our friends at Steiger's Ace Hardware for helping get these windows ordered and delivered on time! And a big shout out to our in-house team for all of their hard work so far this summer. It's been awesome to see the impressive things they're capable of.

Jonah, Austin and Cameron installing a window in the Gabbro Suites. - 7/8/2023

Rope Work

Even with a huge list of projects on deck for the new lift, we still have to set aside time to maintain our existing fleet. The Bear Creek Double is in need of a replacement haul rope this summer and today (7/8) we began the process of installing the old rope from the Original Double. While I call it an "old rope" it was replaced less than 10 years ago, so we expect it to have another 20 or so years of life left in it. This is a time-consuming process that requires the existing rope to be spliced into the new one before spooling up the old rope on a giant winch. As the old rope is wound up, the new one is pulled off of its spool and around the entire lift. Once pulled around the two ends of the new rope we'll pull it tight to allow us to splice it together into a single loup. 

Our team working with Mountain Wire Rope to install the new haul rope on Bear Creek - 7/8/2023

Once the splice is complete, the rope will be lifted back onto the towers, the lift tensioned and the chairs rehung. Once rehung we plan to repaint the chairs on this lift to freshen them up and improve the protection for the metal to prevent rusting. 

While under tension the cables slowly stretch out over time and there is only so much ability to accommodate the additional length within the tension terminal. Every so often we need to open the splice back up and shorten it to remove the excess length. This summer we need to do that on B and D lifts over at Black River Basin. Mountain Wire Rope is also going to help us out with that on this visit.

With so much going on around here it really is hard to keep up with it all. I'll do my best to keep you posted on all the happenings, but you'll probably have to come visit this winter to appreciate all that we've been working on this summer!

Looking towards winter.

-Benjamin

Comments

Popular posts from this blog

Opening Weekend at Jackson Creek Summit

 Yesterday was opening day at Jackson Creek Summit. It was exciting to welcome guests into the renovated Summit Center, now named the Sugar Maple Chalet. It was fun to watch our long time season pass holders check out all the changes we'd made to a place they've been so familiar with over the years. Who knew carpeting and anti-slip vinyl flooring could be such an exciting change.  The rental shop is finally finished and welcomed it's first renters yesterday. The space turned out great thanks to the hard work from many hands. It's so neat to see families get outfitted in their gear before heading straight onto the beginner slopes, just a few steps away. Our staff particularly appreciates the opportunity to watch their customers take their first turns, instead of being stuck in the windowless shop they previously called home.  We did have a few hang-ups in our plan that caused us to modify our operations for opening day and the rest of the weekend. As part of the construc...

A Flurry of Activity

The Sugar Maple Chalet (former Summit Center) is really starting to come together, with renovations wrapping up in preparation for our opening day this Friday. Between contractors and our own team, there is quite the flurry of activity going on as I write this morning. We're going to be running down to the wire with a number of finishing touches. The new ticket windows are nearing completion, with just the windows themselves yet to be installed. Delivery is scheduled for Wednesday, and the crew will get to work on installing them as soon as they arrive. In the meantime, we'll be working on setting up the computers with our point-of-sale systems to be ready for our guests on Friday. Once complete, all day tickets and rentals will be sold out of these windows. Season pass pickup will be available at the guest service counter inside the chalet. The new carpet, paint, and furniture has made a tremendous difference inside the chalet. The classic charm of the building really shines w...

Just Getting Started

I had the opportunity to get out skiing with my Dad and my Sister on Sunday to wrap up the weekend. It was great to be out on the snow. Shanty Boy was a blast. Smooth, fast, and steep. Was fun to think that we're really just getting started, with so much more terrain to open and enjoy this season. The conditions were made even better by my brand new boots from Big Snow Outfitters in Bessemer. Growing up, my first few pairs of skis and boots all came from BSO's retired rental fleet, so of course it was the first place I thought to look to get my slightly packed out boots fitted properly. Walking into the store brought back so many childhood memories of stopping by the store after a day of skiing to enjoy the warmth of the wood burning fire and browse around dreaming of what equipment I'd buy when I grew up. The nostalgia must have got to me because it wasn't long before I was walking out with a new pair of Lange boots. Apparently the boots I'd been rocking for the pa...