Concrete Time

With all of the snow melted and the hill dried out, the team from Ruotsala has focused their efforts on getting each of the tower foundations poured. The new lift will have 10 total towers along the line. Tower 1 sits immediately outside the bottom terminal, and tower 10 is just downhill from the top terminal. Those two tower bases will be excavated and poured alongside their respective terminal foundations. For now, our work has begun at tower 9, near the summit, and is progressing downhill as the access road gets built.  The first step of each tower build is to excavate the tower location down to the precise elevation required according to the size and height of the footing. Once excavated and elevations are verified, soil bearing analysis must be completed to ensure the soil conditions are suitable for the new tower to be placed on. Our friends at Coleman Engineering out of Ironwood perform a series of tests in each excavation to evaluate the soil's ability to bear weight. Once