Skip to main content

Concrete Time

With all of the snow melted and the hill dried out, the team from Ruotsala has focused their efforts on getting each of the tower foundations poured. The new lift will have 10 total towers along the line. Tower 1 sits immediately outside the bottom terminal, and tower 10 is just downhill from the top terminal. Those two tower bases will be excavated and poured alongside their respective terminal foundations. For now, our work has begun at tower 9, near the summit, and is progressing downhill as the access road gets built. 

The first step of each tower build is to excavate the tower location down to the precise elevation required according to the size and height of the footing. Once excavated and elevations are verified, soil bearing analysis must be completed to ensure the soil conditions are suitable for the new tower to be placed on. Our friends at Coleman Engineering out of Ironwood perform a series of tests in each excavation to evaluate the soil's ability to bear weight. Once their tests are complete and they give the okay, Ruotsala's team gets to work building the forms for the base of the footer.

Footing base forms set and ready for the first pour at Tower 9. -05/25/2023

Freshly poured base for Tower 9's footing. - 05/30/2023

After the initial pour is complete and curing has begun, the initial forms are stripped and the work begins to build the cage for the concrete pier. This section contains the anchor bolts that will secure the lift tower to the concrete base. This is a critical portion of the build as each anchor bolt's location needs to be precisely in the right location to align with the pattern specific to each tower. Our project manager from Dopplemayr uses special surveying equipment to verify the correct location of each anchor bolt before the pour is authorized. 

Tower 9's pier formed up and ready for the final pour. - 06/02/2023

Last week (week of May 29th) the footing bases were poured on 9, 8, and 7 while the forms were prepped on 6, 5, and 4. This week (week of June 5th) the concrete trucks will be back on site to pour the piers for 7-9 and the bases for 4-6. The image below shows the approximate location of each tower along the new lift line. If you look closely you can see the access road that has been carved into the hillside to allow concrete trucks to make their way down to each of the tower sites. Getting all of the tower concrete poured will be a huge milestone for the project and if the weather continues to be in our favor, we may see this wrap-up by the end of June. 

On-hill progress as of June 1st, 2023.

The new lift is slowly coming to life more and more each day. I truly can't wait to see how it will transform the ski area and look forward to welcoming you all back to the slopes this winter. For now, enjoy the summer weather and if you're in the area, stop by Jack's on Friday or Saturday to check out the progress from the deck while enjoying a nice cold beverage. 


See ya out there! - Benjamin

Comments

Popular posts from this blog

Opening Weekend at Jackson Creek Summit

 Yesterday was opening day at Jackson Creek Summit. It was exciting to welcome guests into the renovated Summit Center, now named the Sugar Maple Chalet. It was fun to watch our long time season pass holders check out all the changes we'd made to a place they've been so familiar with over the years. Who knew carpeting and anti-slip vinyl flooring could be such an exciting change.  The rental shop is finally finished and welcomed it's first renters yesterday. The space turned out great thanks to the hard work from many hands. It's so neat to see families get outfitted in their gear before heading straight onto the beginner slopes, just a few steps away. Our staff particularly appreciates the opportunity to watch their customers take their first turns, instead of being stuck in the windowless shop they previously called home.  We did have a few hang-ups in our plan that caused us to modify our operations for opening day and the rest of the weekend. As part of the construc...

A Flurry of Activity

The Sugar Maple Chalet (former Summit Center) is really starting to come together, with renovations wrapping up in preparation for our opening day this Friday. Between contractors and our own team, there is quite the flurry of activity going on as I write this morning. We're going to be running down to the wire with a number of finishing touches. The new ticket windows are nearing completion, with just the windows themselves yet to be installed. Delivery is scheduled for Wednesday, and the crew will get to work on installing them as soon as they arrive. In the meantime, we'll be working on setting up the computers with our point-of-sale systems to be ready for our guests on Friday. Once complete, all day tickets and rentals will be sold out of these windows. Season pass pickup will be available at the guest service counter inside the chalet. The new carpet, paint, and furniture has made a tremendous difference inside the chalet. The classic charm of the building really shines w...

Just Getting Started

I had the opportunity to get out skiing with my Dad and my Sister on Sunday to wrap up the weekend. It was great to be out on the snow. Shanty Boy was a blast. Smooth, fast, and steep. Was fun to think that we're really just getting started, with so much more terrain to open and enjoy this season. The conditions were made even better by my brand new boots from Big Snow Outfitters in Bessemer. Growing up, my first few pairs of skis and boots all came from BSO's retired rental fleet, so of course it was the first place I thought to look to get my slightly packed out boots fitted properly. Walking into the store brought back so many childhood memories of stopping by the store after a day of skiing to enjoy the warmth of the wood burning fire and browse around dreaming of what equipment I'd buy when I grew up. The nostalgia must have got to me because it wasn't long before I was walking out with a new pair of Lange boots. Apparently the boots I'd been rocking for the pa...